File #: 20-048-4    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 3/31/2020 In control: Operations Committee
On agenda: 4/15/2020 Final action: 4/27/2020
Title: Award of Contract J06066C03, Protective Relay Upgrades at Jones Island Water Reclamation Facility, and Approve Changes in Total Project Costs
Sponsors: Executive Director
Attachments: 1. 01_OP_Award_J06066C03_Protective_Relay_Upgrade_legislative_file.pdf, 2. 01_OP_Award_J06066C03_Protective_Relay_Upgrade_fiscal note.pdf, 3. 01_OP_Award_J06066C03_Protective_Relay_Upgrade_SWMBE.pdf

Title

Award of Contract J06066C03, Protective Relay Upgrades at Jones Island Water Reclamation Facility, and Approve Changes in Total Project Costs

Body

RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that Contract J06066C03, Protective Relay Upgrades at Jones Island Water Reclamation Facility, is awarded to Pieper Electric, Inc., in the amount of $958,750, and that the Executive Director is directed to execute the contract on behalf of the District.

 

FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the total project cost for Project J06066, Power System Improvements, is increased by $386,890 for an amended total project cost of $2,023,630, and that a corresponding change is made to the total project cost for Project J99001, Allowance for Cost and Schedule Changes.