26-004-1
| 8 | | | Reports | Operations and Maintenance Report for July and August 2026 - Pat Obenauf & Brett Kelly | | |
Not available
|
Not available
|
|
26-096-9
| 1 | 1 | | Resolution | Award of Contract P-3216, Service Agreement for Operations and Maintenance of Water Reclamation Infrastructure | | |
Not available
|
Not available
|
|
26-097-9
| 1 | 2 | | Resolution | Contracts P-3216-1, Operations and Maintenance Contractor Computerized Maintenance Management System Implementation Support, and P-3216-2, Operations and Maintenance Contractor Pre-Term Transition Services | | |
Not available
|
Not available
|
|
26-098-9
| 1 | 3 | | Resolution | Approval of 2026 Green Solutions Program Projects G98005P173 Change Order 1, G98005P179 Change Order 1, G98005P193, and G98005P194 | | |
Not available
|
Not available
|
|
26-099-9
| 1 | 4 | | Resolution | Change Order Request, Funding Agreement M10005EG03 Under Project M10005, 2025 Village of Elm Grove Private Property Infiltration and Inflow Reduction Project | | |
Not available
|
Not available
|
|
26-100-9
| 1 | 5 | | Resolution | Award of Contract P01005C13, Waste Activated Sludge Receiving Pump Motor and Density Meter Improvements - Interplant Sludge System Improvement | | |
Not available
|
Not available
|
|
26-101-9
| 1 | 6 | | Resolution | Change Order Request, Contract I98007P01, Planning Services - Inline Storage System Ventilation and Odor Study, and Restore the Executive Director’s Original Authority | | |
Not available
|
Not available
|
|
26-102-9
| 1 | 7 | | Resolution | Award of Contract W20033C01, Hart Park and Western Milwaukee Levee System - Freeboard Improvements; Change Order Request, Contract TS-2683, On-Call Levee System Engineering and Accreditation Services; and Restore Executive Director’s Original Delegated Authority | | |
Not available
|
Not available
|
|
26-103-9
| 1 | 8 | | Resolution | Change Order Request and Delegate Executive Director Change Order Authority, Contract TS-2726, Project Engineering Services - Wastewater Conveyance and Treatment Facilities | | |
Not available
|
Not available
|
|
26-104-9
| 1 | 9 | | Resolution | Delegate Executive Director Change Order Authority, Contract J06087C07, Product Cooler 1 Rehabilitation at the Jones Island Water Reclamation Facility | | |
Not available
|
Not available
|
|
26-105-9
| 1 | 10 | | Resolution | Award of Contract S06059C01, Solar Panel Installation Phase 1 at South Shore Water Reclamation Facility | | |
Not available
|
Not available
|
|
26-106-9
| 1 | 11 | | Resolution | Change Order Request, Contract C03013D01, Engineering Services - Oklahoma Avenue Metropolitan Interceptor Sewer Capacity Improvements, and Restore the Executive Director’s Original Authority | | |
Not available
|
Not available
|
|
26-108-9
| 1 | 12 | | Resolution | Award of Contract M01045C01, Modifications at Headquarters Boat Dock, and Approve Changes in Total Project Cost | | |
Not available
|
Not available
|
|
26-109-9
| 1 | 13 | | Resolution | Agreement between the Milwaukee Metropolitan Sewerage District and City of Wauwatosa Regarding the Martha Washington/Highlands Metropolitan Interceptor Sewer Rehabilitation, Project C04005 | | |
Not available
|
Not available
|
|
26-110-9
| 1 | 14 | | Resolution | Authorization to Execute Professional Services Agreement S04037P02, Biosolids Alternatives Evaluation | | |
Not available
|
Not available
|
|
26-111-9
| 1 | 15 | | Resolution | Insurance Coverage Purchase or Renewal for General Operations | | |
Not available
|
Not available
|
|
26-003-1
| 8 | | | Reports | EXECUTIVE DIRECTOR’S REPORT
A. Monthly Reports
B. Staff Recognition (Kevin Shafer)
C. Update on Menomonee River Flood Management Projects (Jennifer Wright and Mark Mittag)
D. NACWA Peak Performance Awards (Kevin Shafer) | | |
Not available
|
Not available
|