26-004-1
| 3 | | | Reports | Operations and Maintenance Report for February 2026 - Pat Obenauf & Paul Keppler | | |
Not available
|
Not available
|
|
26-031-3
| 1 | 1 | | Resolution | Award of Contract W29002D01, Engineering and Ecological Design Services - Burnham Canal Wetland Restoration | | |
Not available
|
Not available
|
|
26-032-3
| 1 | 2 | | Resolution | Approval of Funding Agreement M10005MI14 Under Project M10005, 2026 City of Milwaukee Private Property Infiltration and Inflow Reduction Project | | |
Not available
|
Not available
|
|
26-033-3
| 1 | 3 | | Resolution | Contract J06104E01, Preliminary Engineering Services, Jones Island Turbine Generator System Improvements | | |
Not available
|
Not available
|
|
26-034-3
| 1 | 4 | | Resolution | Award of Contract J01019C01, Jones Island Force Main Improvements, and Approve Changes in Total Project Cost | | |
Not available
|
Not available
|
|
26-035-3
| 1 | 5 | | Resolution | Change Order Request, Contract J06083D01, Engineering Services - Heating, Ventilation, and Air Conditioning System Improvements in Buildings 234, 235, 243, and 256, and Restore the Executive Director’s Original Authority | | |
Not available
|
Not available
|
|
26-036-3
| 1 | 6 | | Resolution | Award of Contract S06046C03, Cat Engine 1, 2, 3, and 4 Major Overhauls at South Shore Water Reclamation Facility | | |
Not available
|
Not available
|
|
26-037-3
| 1 | 7 | | Resolution | Change Order to Contract P02006C01, Management, Operation, Maintenance, and Emergency Response Services for the Landfill Gas Pipeline | | |
Not available
|
Not available
|
|
26-038-3
| 1 | 8 | | Resolution | Declaration of Excess Land and Authorization to Transfer One Greenseams® Purchased Property (Hubacek) in the Milwaukee River Watershed | | |
Not available
|
Not available
|
|
26-039-3
| 1 | 9 | | Resolution | Declaration of the Public Necessity and Approval of the Acquisition Plat (Relocation Order) for the Mill Road Metropolitan Interceptor Relief Sewer, Project C04010 | | |
Not available
|
Not available
|
|
26-040-3
| 1 | 10 | | Resolution | Authorizing the Executive Director to Execute a Contract with i3 Verticals for a Three-year Agreement for Hyland OnBase, the District’s Electronic Records Management System | | |
Not available
|
Not available
|
|
26-003-1
| 3 | | | Reports | EXECUTIVE DIRECTOR’S REPORT
A. Monthly Reports
B. Staff Recognition (Kevin Shafer)
C. Green Luminaries (Jamie Ferschinger)
D. Wisconsin Department of Natural Resources Project Partnership Award (Jamie Ferschinger)
E. 2025 Annual Performance Review (Alex Klosterman)
F. Veolia Year in Review (Paul Keppler)
G. Green Lab Certification (Jessica Nanes) | | |
Not available
|
Not available
|