Award of Contract C01006E02, Metropolitan Interceptor Sewer Condition Assessment Project, and Approve Changes in Total Project Cost
Body
RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that Contract C01006E02, Metropolitan Interceptor Sewer Condition Assessment Project, is awarded to Mid City Corporation, in an amount not to exceed $1,047,200, and that the Executive Director is directed to execute a contract on behalf of the District.
FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the total project cost for Project C01006, Metropolitan Interceptor Sewer Condition Assessment Project, is increased by $130,000 for an amended total project cost of $1,530,858, and that a corresponding change is made to the total project cost for Project M99001, Allowance for Cost and Schedule Changes.