File #: 21-078-6    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 6/3/2021 In control: Operations Committee
On agenda: 6/14/2021 Final action: 6/28/2021
Title: Award of Contract J04061C03, Programmable Logic Control 5 Upgrade in the Dewatering and Drying Facility (Rebid), and Approve Changes in Total Project Cost
Sponsors: Executive Director
Attachments: 1. 02_OP_Award_J04061C03_Dewatering_and_Drying_PLC5_Upgrade_legislative_file.pdf, 2. 02_OP_Award_J04061C03_Dewatering_and_Drying_PLC5_Upgrade_fiscal_note.pdf, 3. 02_OP_Award_J04061C03_Dewatering_and_Drying_PLC5_Upgrade_SWMBE.pdf

Title

Award of Contract J04061C03, Programmable Logic Control 5 Upgrade in the Dewatering and Drying Facility (Rebid), and Approve Changes in Total Project Cost

Body

RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that Contract J04061C03, Programmable Logic Control 5 Upgrade in the Dewatering and Drying Facility (Rebid), is awarded to Allan Integrated Control Systems, Inc., in the amount of $2,744,900, and that the Executive Director is directed to execute a contract on behalf of the District.

 

FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the total project cost for Project J04061, Dewatering and Drying Programmable Logic Control 5 Upgrades, is decreased by $1,158,039 for an amended total project cost of $6,740,000, and that a corresponding change is made to the total project cost for Project M99001, Allowance for Cost and Schedule Changes.