Title
Award of Contracts J01019E01 and C07037E01, Jones Island and South Shore Force Main Condition Assessment, and Approve Change in Total Project Cost
Body
RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the Executive Director is authorized and directed to execute Contract J01019E01, Jones Island Force Main Condition Assessment, with Mid City Corporation in an amount of $265,000 and Contract C07037E01, South Shore Force Main Condition Assessment, with Mid City Corporation in an amount of $780,000.
FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the total project cost for Project C07037, South Shore Force Main Assessment, is increased by $92,886 for an amended total project cost of $1,082,310, and that a corresponding change is made to the total project cost for Project M99001, Allowance for Cost and Schedule Changes.