Title
Award of Contract S03003C03, Disinfection Improvements at South Shore Water Reclamation Facility, and Approve Changes in Total Project Costs
Body
RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that Contract S03003C03, Disinfection Improvements at South Shore Water Reclamation Facility, is awarded to J. F. Ahern Co. in the amount of $1,090,389, and that the Executive Director is directed to execute a contract on behalf of the District.
FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the total project cost for Project S03003, Post-Secondary Capacity Improvements, is increased by $647,740 for an amended total project cost of $2,642,674, and that a corresponding change is made to the total project cost for Project S99001, Allowance for Cost and Schedule Changes.