Title
Award of Contract P01005C01, Interplant Sludge System - Corrosion Monitoring System Improvements, and Contract TS-2664, Resident Engineering Services; and Approve Change in Total Project Cost
Body
RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that Contract P01005C01, Interplant Sludge System - Corrosion Monitoring System Improvements, is awarded to Terra Engineering & Construction Corporation in the amount of $8,122,650 and that the Executive Director is directed to execute a contract on behalf of the District.
FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the Executive Director is authorized to execute Contract TS-2664, Resident Engineering Services, with R.A. Smith National, Inc., in an amount not to exceed $250,000.
FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the total project cost for Project P01005, Interplant Pipeline Improvements - Phase II, is increased by $3,728,200 for an amended total project cost of $20,411,613 and that a corresponding change is made to the total project cost for Project M99001, Allowance for Cost and Schedule Changes.