Title: Award of Contract C98051C01, Conveyance Gate Rehabilitation Phase 3 Project, Contract TS-2634, Resident Engineering Services, and Approve Changes in Total Project Costs
Sponsors: Executive Director
Attachments: 1. 01_OP_AW_C98051_ConvGate_legislative_file.pdf, 2. 01_OP_AW_C98051_ConvGate_fiscal_note.pdf, 3. 01_OP_AW_C98051_ConvGate_SWMBE1.pdf, 4. 01_OP_AW_C98051_ConvGate_SWMBE2.pdf

Title

Award of Contract C98051C01, Conveyance Gate Rehabilitation Phase 3 Project, Contract TS-2634, Resident Engineering Services, and Approve Changes in Total Project Costs

Body

RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that Contract C98051C01, Conveyance Gate Rehabilitation Phase 3 Project, is awarded to J. F. Ahern Company in the amount of $2,738,000, and that the Executive Director is directed to execute a contract on behalf of the District.

 

FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the Executive Director is authorized to execute Contract TS-2634 with R.A. Smith National, Inc., in an amount not to exceed $120,000.

 

FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the total project cost for Project C98051, Conveyance Gate Rehabilitation Phase 3 Project, is increased by $637,594 for an amended total project cost of $3,712,733, and that a corresponding change is made to the total project cost for Project M99001, Allowance for Cost and Schedule Changes.