Change Order Request, Contract S03005D01, Engineering Services - Disinfection Process Improvements at South Shore Water Reclamation Facility, and Restore the Executive Director’s Original Delegated Authority
Body
RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the Executive Director is authorized to execute a change order to Contract S03005D01, Engineering Services - Disinfection Process Improvements at South Shore Water Reclamation Facility, with Carollo Engineers, Inc., in an amount not to exceed $100,607, and that the Executive Director’s original delegated authority is restored.