Title: Contract W11031D11, Environmental Engineering Services - 30th Street Corridor Phase 2 West Basin
Sponsors: Executive Director
Attachments: 1. 01_OP_Award_W11031D11_30th_St_Corridor_West_Basin_Environmental_legislative_file.pdf, 2. 01_OP_Award_W11031D11_30th_St_Corridor_West_Basin_Environmental_fiscal_note.pdf, 3. 01_OP_Award_W11031D11_30th_St_Corridor_West_Basin_Environmental_SWMBE.pdf

Title

Contract W11031D11, Environmental Engineering Services - 30th Street Corridor Phase 2 West Basin

Body

RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the Executive Director is authorized to execute on behalf of the District Contract W11031D11, Environmental Engineering Services - 30th Street Corridor Phase 2 West Basin, with Ramboll Americas Engineering Solutions, Inc., in an amount not to exceed $801,946.