File #: 24-129-10    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 9/30/2024 In control: Operations Committee
On agenda: 10/14/2024 Final action: 10/28/2024
Title: Change Order Request, Contract C04010D01, Engineering Services - Mill Road Metropolitan Interceptor Sewer Relief Sewer, and Restore Executive Director’s Original Delegated Authority
Sponsors: Executive Director
Attachments: 1. 04_OP_C04010D01_Mill_Road_MIS_CO_legislative_file.pdf, 2. 04_OP_C04010D01_Mill_Road_MIS_CO_fiscal_note.pdf, 3. 04_OP_C04010D01_Mill_Road_MIS_CO_attachment.pdf

Title

Change Order Request, Contract C04010D01, Engineering Services - Mill Road Metropolitan Interceptor Sewer Relief Sewer, and Restore Executive Director’s Original Delegated Authority

Body

RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the Executive Director is authorized to execute a change order to Contract C04010D01, Engineering Services - Mill Road Metropolitan Interceptor Sewer Relief Sewer, with Mead & Hunt, Inc., in an amount not to exceed $1,400,452, and that the Executive Director’s original delegated authority is restored.