Approve Changes in Total Project Cost for Project J06073, Harbor Siphons Area Settlement Mitigation
Body
RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the total project cost for Project J06073, Harbor Siphon Area Settlement Mitigation, is increased by $500,000 for an amended total project cost of $1,032,400, and that a corresponding change is made to the total project cost for Project M99001, Allowance for Cost and Schedule Changes.