Title
Change Order Request, Contract M06016C06, Enterprise Resource Planning System Implementation and Approve Changes in Total Project Cost - Project M06016
Body
RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the Executive Director is authorized to execute a change order to Contract M06016C01, Enterprise Resource Management System Implementation, with Protiviti, Inc., in an amount not to exceed $480,000.
FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the total project cost for Project M06016, Enterprise Resource Planning System Implementation, is increased by $580,000 for an amended total project cost of $16,824,008 and that a corresponding change is made to Project M99001, Allowance for Cost and Schedule Change.