Award of Contract S06050C01, Heating, Ventilation, and Air Conditioning System Improvements at South Shore Water Reclamation Facility; Change Order Request, Contract S06050D01, Engineering Services - Heating, Ventilation and Air Conditioning System Improvements in Buildings 378 and 380; Restore Executive Director’s Original Delegated Authority; and Approve Changes in Total Project Cost
Body
RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that Contract S06050C01, Heating, Ventilation, and Air Conditioning System Improvements at South Shore Water Reclamation Facility, is awarded to Zien Mechanical Contractors in the amount of $1,596,339, and that the Executive Director is directed to execute a contract on behalf of the District.
FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the Executive Director is authorized to execute a change order to Contract S06050D01, Engineering Services - Heating, Ventilation, and Air Conditioning System Improvements in Buildings 378 and 380, with TYLin in an amount not to exceed
$18,323, and that the Executive Director’s original delegated authority is restored.
FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the total project cost for Project S06050, Maintenance & Administration Buildings (378 & 380) Heating, Ventilation, and Air Conditioning System Improvements, is increased by $100,000 for an amended total project cost of $2,618,000, and that a corresponding change is made to the total project cost for Project M99001, Allowance for Cost and Schedule Changes.