File #: 25-032-3    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 2/24/2025 In control: Operations Committee
On agenda: 3/10/2025 Final action: 3/24/2025
Title: Change Order Request, Contract S06038C34, Digester #12 Heat Exchanger and Hot Water Pump Replacements at the South Shore Water Reclamation Facility, and Increase Executive Director’s Change Order Authority
Sponsors: Executive Director
Attachments: 1. 03_OP_Change_Order_S06038C34_Increase_ED_Authority_legislative_file.pdf, 2. 03_OP_Change_Order_S06038C34_Increase_ED_Authority_Fiscal_Note.pdf

Title

Change Order Request, Contract S06038C34, Digester #12 Heat Exchanger and Hot Water Pump Replacements at the South Shore Water Reclamation Facility, and Increase Executive Director’s Change Order Authority

Body

RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the Executive Director is authorized to execute a change order to Contract S06038C34, Digester #12 Heat Exchanger and Hot Water Pump Replacements at the South Shore Water Reclamation Facility, with Lee Mechanical, Inc., in an amount not to exceed $29,535.

 

FURTHER RESOLVED, by the Milwaukee Metropolitan Sewerage Commission, that the Executive Director is delegated $50,000 in change order authority for future change orders to Contract S06038C34, Digester #12 Heat Exchanger and Hot Water Pump Replacements at the South Shore Water Reclamation Facility.